Defect Handling Flowchart +-+ Test member submits defect +-+Cedar
2024-08-27 10:17:56 1 Report
Log in to view full content
This flowchart, titled 'Defect Handling Flowchart - Test member submits defect - Cedar,' outlines the process for managing defects within a project. It begins with a test member submitting a defect and proceeds through various stages, including confirming the test target version, assigning the defect, and setting its status as verified, suspended, or resolved. The flowchart involves key roles such as development and project leaders, who review and analyze defects, determine solutions, and ensure on-site verification if necessary. Regular reviews and status updates ensure that defects are effectively managed until they are resolved or closed.
Other works by the author
Outline/Content
Confirm
Label transfer test target version
No
Yes
Development leader
Note: Analysis progress and reasons for unresolved issues
New
Status set to [Verified]
Status set to 【Suspended】
Review
End
Regular cleaning (1~3 months)
On-site pass
Status set to 【Assigned】
Hang up?
State set to [ReOpen]Set the corresponding return result
On-site verification is required.
Status set to [Resolved]Remarks:Defect causeSolution
Develop human solutions
Solved
Defect Handling Flowchart - Test member submits defect
Status set to 【Assigned】Note: Close decision opinion
Project leader
Test members
beyond the observation period
Need to review
Status set to [Closed]
Regression through