Defect Handling Flowchart +-+ Test member submits defect +-+Cedar

2024-08-27 10:17:56 1 Report
This flowchart, titled 'Defect Handling Flowchart - Test member submits defect - Cedar,' outlines the process for managing defects within a project. It begins with a test member submitting a defect and proceeds through various stages, including confirming the test target version, assigning the defect, and setting its status as verified, suspended, or resolved. The flowchart involves key roles such as development and project leaders, who review and analyze defects, determine solutions, and ensure on-site verification if necessary. Regular reviews and status updates ensure that defects are effectively managed until they are resolved or closed.